Approved
3 Feb 2024 — 1 Apr 2025

Temporary Road Closure - Bail Street

Applicant: Nelson Marlborough Traffic Management
Event: The closures are to enable crane lifts for the development at 9 Bail Street
Proposed Closures: Bail Street – number 7 Bail Street to end of street
Date and time of scheduled closure: Road closures will occur periodically over the next 13 months (3 February 2024 – 1 April 2025) between the hours of 6:00 am and 6:00 pm.
Businesses and residents on Bail Street will be delivered a letter 48 hours prior to closures occurring.

Approved
11 Mar 2024 — 28 Feb 2025

Temporary Road Closure - Wakatu Lane - Trafalgar Street entrance

Applicant: Comans Construction
Event: Demolition and Construction of Building 7 Wakatu Lane and 51 Bridge Street.
Location:  Wakatu Lane - Trafalgar Street entrance
Date and time of scheduled closure: Monday 11 March to Friday 28 February 2025 – Closed 24/7.
Note: this proposal is for an entire year. 

The entrance will be open to vehicles and pedestrians over the Christmas Holiday period:
Date of opening for Christmas -             20 Dec 2024
Date of closure post-Christmas -           13 January 2025
Date of permanent re-opening -             1 March 2025

The closure is for the demolition of 51 Bridge Street and the construction of a new building.  
Vehicle access to and from Wakatu Square will via Rutherford Street only.
No Pedestrian access will be available.

Approved
20 Jan 2025 — 21 Mar 2025

Temporary Road Closure - Washington Terrace

Applicant: Nelmac
Event: Renewal of the wastewater and water pipe along Washington Terrace
Location: Washington Terrace – full length
Date and time of scheduled closure: Monday 20 January to Friday 21 March 2025 – closed at all times for the duration of the work.

Approved
20 Jan 2025 — 12 Feb 2025

Temporary Road Closure - Kakenga Road

Applicant: Ground Breaking Contracting Limited
Event: Power pole replacement
Location: Kakenga Road - between no.1 and no.5
Date and time of scheduled closure: Monday 20 January to Wednesday 12 February 2025 – 7:00 am to 5:00 pm
Please note: The road will only be closed periodically within this timeframe – residents will be given 48 hours’ notice of each closure via a letter drop from the contractor. Total closure time will be 1-3 days, weather dependent)
Contingency dates and times when closure may occur: Contingency is included in the above dates

Approved
9 Feb 2025 — 21 Feb 2025

Temporary Road Closure - Washington Road/St Vincent Street Roundabout (NIGHTWORKS)

NIGHTWORKS

Applicant: Fulton Hogan
Event: Resealing the surface of the road with asphalt
Location: Washington Road/St Vincent Street Roundabout - and associated arterial streets:

  • Washington Road – between Arrow Street & St Vincent Street
  • Hastings Street – between Washington Road & Pioneer Crescent
  • Watson Street – full length
  • St Vincent Street – between Natalie Street & the Countdown Carpark
  • Gloucester Street – between St Vincent & Vanguard Street

Date and time of scheduled closure: Sunday 9 February to Friday 21 February 2025 – 7:00 pm to 5:00 am (the roads will be closed overnight only – open during the day)
Contingency dates and times when closure may occur: Sunday 2 March to Friday 14 March 2025 – 7:00 pm to 5:00 am (the roads will be closed overnight only – open during the day)

Proposed
12 Feb 2025 — 14 Feb 2025

Proposed Temporary Road Closure - Gloucester Street

Applicant: Asphalt & General
Event: The closure will allow Nelmac and Delta to carry out open trench work required for electrical upgrades.
Location: Gloucester Street at the Kerr Street/Konini Street intersection
Date and time of scheduled closure: Wednesday 12 February to Friday 14 February – 6:00 am on the first day until 6:00 pm on the last day (this is a 24 hour closure)
Contingency dates and times when closure may occur: Contingency is included in the dates above

  • Vehicle access for residents/businesses, couriers and home help will be available via Wellington Street and Mount Street. There will be one-way northbound exit to Hardy Street via Konini Street/Kerr Street. There will be no access from Gloucester Street. Delays are likely.

Proposed
2 Mar 2025

Proposed Temporary Road Closure - Nelson Italian Festival

Applicant: Club Italia Nelson Incorporated
Event: Nelson Italian Festival
Location: Trafalgar Street - between Wainui Street and Grove Street (road closed)
Date and time of scheduled closure: Sunday 2 March 2025. Closed between 6:00 am – 7:00 pm

The event will be run between Wainui Street and Elliott Street.  Resident vehicle access will be available between Elliott Street and Grove Street when safe and directed by the contractor.
Emergency Services access will be catered for.  
Detour will be in place.
The event will run from 10:00 am – 4:00 pm.

Approved
9 Mar 2025

Temporary Road Closure - Sanitarium Weet-Bix Kids TRYathlon

Applicant: Nelson Marlborough Traffic Management
Event: Sanitarium Weet-Bix Kids TRYathlon.

Location: 

  • Tahunanui Recreation Reserve
  • Beach Road from Waikare Street to Golf Road
  • Golf Road from Beach Road to Parkers Road
  • Hounsell Circle
  • Waikare Street
  • Bisley Walk
  • Centennial Road
  • Green Street – from Roto Street

Date and time of scheduled closure: Sunday 9 March 2025. Closed between 6:30 am – 1:30 pm

The roads will be closed. Resident/Business vehicle access will be available when safe and directed by the contractor.
The eBus (Route 4) will be affected by the closure and will operate an alternative route during this time.